How to update Baseline in Primavera P6

Baseline is something we usually do not change. However in some case we need to change it.I will show you how to do it.

Khuong DoMember for 16 years 7 months

Baseline is something we usually do not change. However in some case we need to change it.

I will show you how to do it.

We have a simple project which is assigned a baseline

After a few update period, the project is delayed quite far from the baseline

After discussion with the Owner, they allow us to update our baseline to be identical to current schedule.

There are some ways to update baseline.

Option 1:

We will create a new baseline based on our current schedule and assign the new baseline to our project.

First you have to make an important configuration.

Go to menu Admin -> Admin Preferences.

In Earned Value tab, select “At completion values with current dates”

How to update Baseline in Primavera P6 - 3

Go to menu Project -> Maintain Baselines. Click Add to create a new baseline

How to update Baseline in Primavera P6 - 4

Go to menu Project -> Assign Baselines. Select baseline B2

How to update Baseline in Primavera P6 - 5

Now you can see the baseline have been updated

Option 2 : Restore baseline

Go to menu Project -> Assign Baselines. Select Current project

How to update Baseline in Primavera P6 - 7

Go to menu Project -> Maintain Baselines. Select the baseline and click on Restore button

How to update Baseline in Primavera P6 - 8

Now go to the Project window and we can see the baseline become a normal project which we can open and update easily.

After finish updating the baseline project, you will convert it to become a baseline again.

Open your “main” project. Go to menu Project -> Maintain Baselines. Click on Add button. Now we will select option “Convert another project…”

How to update Baseline in Primavera P6 - 10

And select the updated baseline project

How to update Baseline in Primavera P6 - 11

Now your project will have a new baseline.

Thank you for your time to read this article.

You can also find other post at my personal blog : https://doduykhuong.wordpress.com/