Skip to content
Microsoft Project1 min read

Show summary % complete in Microsoft Project when all subtasks are milestones and some of these milestones are completed

In Microsoft Project, when all subtasks are milestones, the summary percent complete is 0% even when some of the milestones are completed. The summary percent complete only changes to 100% when all the milestones are 100% complete.

Jerome OdehMember for 22 years 8 months

In Microsoft Project, when all subtasks are milestones, the summary percent complete is 0% even when some of the milestones are completed. The summary percent complete only changes to 100% when all the milestones are 100% complete.

This behaviour is as expected as Microsoft Project calculates percent complete using actual duration but since milestones have no duration, a summary task with asll subtasks as milestones would show anything other than 0% or 100% but a lot of people would expect to see intermediate summary percent. For example, if all 5 subtasks are milestones and 2 are 100% complete, the schedule should display 40% for the summary task instead of the 0%.

This tutorial is a workaround that uses custom fields to show intermediate percentages for summary tasks when all subtasks are milestones.

Last updated 30 Oct 2025.

Comments

No comments yet.

Log in or join to comment