Skip to content
General3 min read

What you need to know to close-out your construction project successfully

Many construction projects are financially successful until the end, when costs suddenly spiral out of control. The main reason for the additional costs is because the project isn’t completed on time. When I say completed, I don’t just mean handed over, I mean one hundred percent finished.

Paul NetscherMember for 10 years 1 month

Many construction projects are financially successful until the end, when costs suddenly spiral out of control. The main reason for the additional costs is because the project isn’t completed on time. When I say completed, I don’t just mean handed over, I mean one hundred percent finished.

I’ve visited projects long after they have been completed, yet the contractor’s offices and workers are still on site. I always wonder what this is costing the construction company since I’m sure when they priced the project they didn’t allow for the costs of remaining on the project after it was completed.

So why aren’t projects 100% complete even they physically appear complete? Many Construction Project Managers focus only on handing over the project. However, there’s normally more to a project than this. It includes finalising punch lists, finishing and submitting all paperwork (including as-built drawings, quality data packs, guarantees and warranties) and concluding all the contractual obligations (such as commissioning and testing).

The impacts of not completing construction projects on time

Failure to complete construction projects correctly, including completing all paperwork and documentation, results in increased costs to construction companies due to:

1. the project extending beyond the contractual end date, often resulting in the application of penalties or liquidated damages

2. construction resources remaining on the project longer than budgeted for

3. resources not being released to other construction projects where they’re required, which negatively impacts those projects 4. retention money and sureties being retained longer by the client

5. insurances remaining in place for a longer time

6. the contractor incurring additional overheads, such as the costs of facilities, accommodation, vehicles and security remaining on site longer

Needless to say the failure of the construction company to complete all outstanding items can be very frustrating to clients and they usually incur additional costs for their supervision as well as inconvenience and disruption to their operations.

What needs to be considered

Some of the items which should be considered at the end of the project include:

1. obtaining the certificate of practical completion

2. handing over quality documentation, commissioning data, spare parts lists and warranties to the client

3. handing over all spare parts and client-purchased materials to the client

4. getting the release of sureties or bonds and returning them to the institution which issued them

5. requesting the release of retention

6. putting items of equipment off-hire and transferring them from site

7. clearing unused materials

8. moving personnel records to the head office

9. sorting, filing and archiving project documentation

10. agreeing the final accounts with the client

11. settling accounts with subcontractors and suppliers

12. submitting the final project invoice to the client

13. demobilising all offices and facilities

14. reinstating laydown areas and access roads, including obtaining signed acceptance from the client

15. handing back all accommodation

16. disconnecting services

17. transferring or terminating personnel

18. disposing of project-purchased assets

19. completing the final cost report

The completion schedule/programme

To facilitate the timely completion of the project a completion schedule should be prepared near the end of the project. This would include:

1. finishing the outstanding items

2. commissioning

3. connecting to existing services and structures

4. completion of the contractor’s punch-list items

5. final punch-listing by the client

6. preparation of hand-over documentation such as quality records, commissioning results, operating manuals and guarantees 7. clearing of the temporary site facilities and services

Conclusion

Closing out a project can often be a complicated and time-consuming process that is underestimated and overlooked by Project Managers and staff who may already be anticipating moving to their next projects. If proper planning and preparation is done at an early stage the close out process will be much simpler. It will save costs and frustration to both the client and the contractor’s staff. How you finish a construction project is often how the client remembers the construction company!

(Written by Paul Netscher the author of the acclaimed books ‘Successful Construction Project Management: The Practical Guide’ and ‘Building a Successful Construction Company: The Practical Guide’. His latest book ‘Construction Claims: A Short Guide for Contractors’ has recently been published. These books are available in paperback and e-book from Amazon and other retail outlets. This article is adapted from information included in these books. To read more visit www.pn-projectmanagement.com )

Picture courtesy Stuart Miles at FreeDigitalPhotos.net

Last updated 30 Oct 2025.

Comments

No comments yet.

Log in or join to comment