Time distributed data

Alexandre Faulx-BrioleMember for 23 years 8 months
Created
2
1
0
Hello PowerProject gurus,
I am trying to promote PowerProject 8 in France, a hard work because almost nobody knows about it.
I would like to build a time distributed table in PP8, the same kind of thing MS Project has with Resource Usage; i.e. on the left pane: Resource Name, Allocaton Name, Total Work; on the right pane: daily / weekly / monthly work for the allocation / task, according to the time zone.
All the best

2 replies

Oldest first
  1. 0
    Andrew Pearce ·
    Have you tried submitting your request to ASTA customer services? Help Desk.
  2. 0
    Alexandre Faulx-Briole ·
    Hi there,
    the answer is: tabular report. Of course, you will not be able to enter data in a report, but you will get the effort and / or cost sliced by time period.
    Alexandre