Find & Replace in APP V11

Bill D.Member for 19 years 1 month
Created
3
30
0
Good day PPlanners,

Does APP v11 has the capability to find and replce text just like were doing it in excel. I can’t find this "magic button" anywhere in the APP window. If any one here in the planet can show me the right button," if it has one", I thank you in advance.

Cheers,

Bill

3 replies

Oldest first
  1. 0
    Bo Johnsen ·
    Hi Billy,

    I haven’t been able to locate it either, however, you can fairly quickly highlight an entire column (or columns), copy to Excel, do the find/replace there and then copy back to APP. This only takes 1/2 min. longer than if the feature had been available in APP.

    Regards,

    Bo
  2. 0
    Bill D. ·
    Bo,

    Tnx for the reply. Now Im sure that the button is not really existing.

    Billy
  3. 0
    Andrew Willard ·
    Hi Billy,

    We have just developed an add on that does Find and Replace like Word/Excel. If you would like a copy to try out please email me at andrew.willard@astadev.com.

Log in or join to reply