Create a Baseline View

Lee MallekMember for 21 years 5 months
Created
2
2
0

I have a programme that I have baselined and progress reschedule on a weekly basis in Powerproject.

My client has requested to see a jagged line down the original baseline.

How do you display a progressed baseline only?

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Lee Step 1 Save your

    Hi Lee

    Step 1 Save your original programme in a new file.

    Step 2 Copy Paste your progressed Start End Dates into the new file and DO NOT SAVE IT.

    Step 3 Baseline the copied dates

    Step 4 Close the file without saving it.

    Step 5 Open the file and Add progress to the file and set as jagged.and add the progress to that - leave the progress line jagged.

    Best regards

    Mike Testro

    If yop

  2. 0
    Chris Rymer ·

    Lee Go to View - View -

    Lee

    Go to View - View - Jagged Progress. This wil give you the view that you are after. This shows the baseline but with the jagged progress you need. The current position of the tasks are shown underneath the baseline and can be turned off if required in Format - Bar Chart.

     

    Chris

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?