Current Baseline - Between set periods
In the Open Standard
Craig AdamsMember for 20 years
- Created
- 2
- 4
0
Hello Fellow Asta Travellers,
Would like to create two columns that show specifiic baseline periods from the same baseline - for instance baseline finish dates for year ending 2011 then another column showing 2011 to year ending 2012 out of the same baseline.
Yes could create two baselines however trying to use only one for original baseline (budgeted works) and one for "what if scenarios".
Can anyone help with formula for this?
Look forward to your reply/ies.
Kind regards,
Craig adams