Asta Task per line Mode

Tony SewellMember for 16 years 1 month
Created
3
1
0

I have recieved a programme which has used the Task per line mode to put multiple activites on a single line. Is there a way to put eeach actvity on its own line - apart from expanding the view!!

 

I dont want works on multply lines

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Tony There is no direcr

    Hi Tony

    There is no direcr way that I know of to change the layout electronically.

    There is a cumbersome way round.

    Copy and paste all the top line headings to a spreadsheet.

    Open all the drop down tasks and copy and paste to a new programme.

    Roll up the new tasks to summaries and then copy and paste the summary titles from the spreadsheet.

    Reinstate the missing links between summaries if they were lost in the copy process.

    Best regards

    Mike Testro

  2. 0
    Jessica Nicholls ·

    HelloThere is indeed a way to

    Hello

    There is indeed a way to do this in the software.

    Select the bar that contains the tasks you wish to "separate out"  and then select the "Unroll Tasks" button from the Hierarchy group on the Home Tab of the Ribbon.

    In toolbar mode, this is found on the Bar Chart toolbar.

    For those who want to work the other way round, their is a "Roll tasks up" button to do the opposite.

    Hope this helps

    Jess @ Asta

  3. 0
    Konstantinos Parsalidis ·

    @ JessExcellent tip, thank

    @ Jess

    Excellent tip, thank you!

Log in or join to reply