Histogram To Count Tasks

Chris LothianMember for 19 years 5 months
Created
2
5
0

Hi All,

I'm trying to create a histogram that counts the number of Tasks at the instant in time that have a been alllocated with a cost centre value, rather unsuccessfully at the moment.

Does anyone know how?

Thanks,

Chris.

2 replies

Oldest first
  1. 0
    Rafael Davila ·

    Create a Dummy Resource, make

    Create a Dummy Resource, make it to be a non-leveling resource and assign a unit of this resource to all activities then the histogram for this resource shall display what you are looking for.

  2. 0
    Mike Testro ·

    Hi Chris Alternatively create

    Hi Chris

    Alternatively create a dummy cost item at £1.00.

    Best regards

    Mike Testro