F9 reschedule issue

Chris WilliamMember for 13 years 8 months
Created
4
5
0

All,

when I press f9 for re-scheduling, circle spins but no progress periods  appear on which I do reschedule.

Where these progress periods hide during pressing F9.

Please Help.

Mike: Plz look at this. Its urgent

Regards,

Chris

4 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi ChrisWhat do you mean by

    Hi Chris

    What do you mean by Progress Periods?

    F9 is not the only way to reschedule - I prefer using an Icon in the toolbar or use the ribbon option.

    Best regards

    Mike Testro

  2. 0
    Chris William ·

    Sorry Mike,Here is the full

    Sorry Mike,

    Here is the full detail of the issue
    When I press F9, usually 'Reschedule Progress Period Warning' message comes on my screen showing
    Straighten progess period : none
    Progress entry period : Wk 23 ...
    But unfortunarely once I clicked dont warn again so now this message is not coming on my screen. whats problem?
    How to bring it back this Reschedule Warning message?
    Please help.
    Thank you
     

  3. 0
    Mike Testro ·

    Hi ChrisHere is an extract

    Hi Chris

    Here is an extract from the PP help section.

    This should do it

    Best regards

    Mike T.

    Some warning and notification prompts within Asta Powerproject include a check box that you can select if you do not want to be notified with the same information again. If you select this check box in a warning or notification prompt, the prompt will not appear the next time the same situation arises.

    You can specify that if you ask not to be warned again when a prompt appears, this should apply permanently, or only to the current session. You can also restore all prompts that you have turned off in the past, so that all prompts are once more shown at the appropriate time.

    To specify the way in which to deal with warning and notification prompts that give you the option not to be warned again:

    1. Click the Tools tab, then click Options. The Options dialog appears.
    2. Click the General tab.
    3. Click Do Not Show Me Again Prompts. The Show Prompts dialog appears.
    4. In the When responding to "Do not show me again" field, select Apply to current session to specify that if you ask not to be warned again when a prompt appears, this should apply only until you close Asta Powerproject, or select Apply permanently to specify that your choice should apply permanently and that the prompt should not appear again when you use Asta Powerproject in the future.
    5. Click Reset to restore all prompts that you have turned off in the past, so that all prompts are once more shown at the appropriate time.
    6. Click OK. 
  4. 0
    Chris William ·

    Mike,Thank you very much for

    Mike,

    Thank you very much for sharing this valuable information. SOLVED

    Regards,

    Chris

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?