How to sort, group and annotate activities properly
- Created
- 2
- 4
Good Afternoon!
I am new user to the Asta powerproject. I researched those questions also before Im asking your help, but did not finde satisfing answer, so hopefully you can help me with the next issues
1) Activity Codes- Does they exist in asta? I have seen several references in booklets, but no guidance how to set them up If there is no activity codes, then what are their replacement? Where can I find the material on how to sort, group and organize tasks. Basically have additional classification
2) Notes on task- is there the possibility to make annotations on a tasklist? Is there a general comment section?
3) Rolling up task- if I mark several tasks and use Roll Task Up button on Home -> Hierarchy, the one left task would look quite ugly. Will be left the name of one task, although ID´s of several. This is not givving overview or summery of rolled up tasks. So the question is can I rename the summary? Can I change the way this one task shows?
All of those tasks basically involves view on the activity list.
I would appreciate your help or any commnet
Karina
2 replies
Oldest firstLog in or join to reply