Using 2 calendars
In the Open Standard
Andrew OwensonMember for 18 years 4 months
- Created
- 4
- 5
0
Hi Guys
I am using two calendars, one with xmas & bank Holidays, and one with just xmas. The one with xmas + bank holidays is the project calendar and the other is applied to some of the activities. When I apply the second calendar to an activity, the bank holiday stops either side of the bar. Is there a way of making the main calendar go over the activities. I dont need anyone to know I am using 2 calendars its just visual.
Many thanks in advance.
Andrew
4 replies
Oldest firstLog in or join to reply