Negative Values For Task Allocations (Cost / Income)

Chris LothianMember for 19 years 6 months
Created
2
35
0

Hi All,

 

Does anyone know if it's possible to have a negative value against a income / cost?

 

Reason for wanting to do this, is that I have an a highway maintenance contract where the client has given us anticipated spends against a list of tasks, but the actual spend was less. Rather than go through and adjust all the anticiapted spends, I was hoping to insert a new task with a negative value against it which represented the sum of the underspend.

 

Kind Regards,

 

Chris

 

2 replies

Oldest first
  1. 0
    Craig Adams ·

    Hi Chris,Wouldn't you just

    Hi Chris,

    Wouldn't you just enter actual cost so you could use Asta cost functions?

    Kind regards,

    Craig

  2. 0
    Ben Taunt ·

    Hi Chris,Whilst I agree with

    Hi Chris,

    Whilst I agree with Craig's suggestion, for reference you can't have a negative cost.  If you try entering one, Asta Powerproject will chuck up a warning stating the value must be greater than zero.  That is the point of the alternative income field within Asta - other software which has no concept of income does allow you to have a negative cost but only to get around that deficency.

    So I guess you could use the income field to record the underspend...?  As the net amount would therefore be orginial cost less the underspend...?  Sounds messy though.

    Cheers,

    Ben @ Asta

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?