Top Down Forecast Entry (Manual)

Adam GarnhamMember for 15 years
Created
1
1
0

Afternoon All,

Hoping you can help me out please.

I am trying to work out how to manually enter forecast & budget values per month. I am happy with bottom up forecasting but more often than not the clients cost engineer creates a monthly rolling forecast (in Excel) that then needs plugging into project/primavera/asta each month against some high level (often WBS level) bars.

Happy with doing this in everything but Asta, so any wisdom on how this can be achieved in Asta would be fab.

Thanks in advance. Adam.

1 reply

Oldest first
  1. 0
    Leigh Durnall ·

    You can copy/paste a region

    You can copy/paste a region of cells between Excel and Asta spreadsheets. Filter out Summary or Expanded tasks though as non-editable values will cause a paste to fail.

    Leigh @ Asta

Log in or join to reply