ASTA File locked when trying to save

Yasine AliMember for 11 years 3 months
Created
2
35
0

Hi everyone,

When trying to save an ASTA file, on the bottom right corner it says something along the lines of "Warning: file could not be saved due to being locked"

Anyone have any ideas on how to unlock it? so the changes on the programme can be saved. 

2 replies

Oldest first
  1. 0
    Barbara McAslan ·

    If you are using the barchart

    If you are using the barchart that has been set up as a 'View', you may have locked the 'View Settings' which is found under the View Properties.

    B

  2. 0
    Yasine Ali ·

    Barbara, thank you for you're

    Barbara, thank you for you're response!

    It was exactly what you said it was, the view was "Locked" in the properties tab.