Importing XML file into Asta

Amir AzadiMember for 14 years 6 months
Created
1
4
0

Hi,

i tried to import a  XML file to Asta, for some reason Asta Split  whatever task longer than 4 days into  several new tasks and roll it up under one task. Is there any way that i can stop this, is there any option in Asta that limits the maximum duration of one Activity?

 

With Thanks

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi AmirI never seem to have

    Hi Amir

    I never seem to have any problem importing Microsoft xml files into Asta - it is probably something in the source file that is causing the split.

    You can try lining up the split tasks and use the Split/Join function to join them into a single task.

    Best regards

    Mike T.