Line of Balance
In the Open Standard
Dean GrimesMember for 9 years 8 months
- Created
- 4
- 4
0
Hi all
I am seeing more and more people wanting a line of balance set up as a spreadsheet, with each plot (housing project) down the left side and each activity along the top with the duration of each task identified, and then in each meeting cell a date of when the activity is to start.
If the activity starts on time it goes green and if it starts late it goes red.
Is there anyway of running a report from Asta to avoid having to manually transfer the info to excel?
Thanks in advance