Nilkamal ParikhMember for 17 years 3 months
Created
0
5
0

Hi,

I have to switch to ASTA from P6 due to my recent move and learning about ASTA everyday. I struggle to do the same thing in ASTA which I can do easily with P6 but I take it as a challange and happy to go for learning this new software.

My questions it is there any function called "Retain Logic" like P6 to maintain the logic alive for out of sequence items? So my task A-B-C are linked finish to start. if my item B is finished out of sequence and still A hasn't finished, why my item C is showing on the status date rather than start after item A?

Can you please help? It's annoying me.

Thanks in advance

Nilkamal

 

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply