Formula in Asta - Slip
In the Open Standard
Paul WoodleyMember for 9 years 11 months
- Created
- 1
- 1
0
Column to show "0"
-If the task is in the past AND 100% complete
-If the task is in the future and 0% complete
Columns to show result from the following formula;
(DateDiff(Start, Today)-[~LP].ActualDuration)
IF
It is in progress and being progressed.
If the task is in the past with 0% progress it should be showing a value. The difference between today and the start of the task (latest progress)
I hope that gives an indication and enough detail as to the requirements.
I am in a bit of a pickle. Hoping someone could shove me in the right direction.
I need the following (regarding slip)
Column value to show "0" IF;
- The task is in the past AND 100% complete
- The task is in the future and 0% complete
Column value to show result from the following formula (the bit I could get to work);
DateDiff(Start,Today)-[~LP].ActualDuration
IF
- The task is in progress
IF the task is in the past with 0% progress it should be showing a value - the difference between today and the start of the task (latest progress)
I hope that gives the detail explicitly enough and hope someone can help out! I am tearing my hair out over this....
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?