Printing - Page Breaks

Dominic PlannerMember for 9 years 4 months
Created
1
4
0

How do I ensure that the page breaks I have inserted into my programme override the pages I have scaled to, when printing?

At present, the number of pages scaled to seems to be taking precendence and it's not taking into consideration when I have applied page breaks to split my programme. 

 

Thanks 

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi DominicGo toPrint >

    Hi Dominic

    Go to

    Print > Options > Scaling > Fit Lines per Page (bottom right corner) > Insert nr of Lines

    best regards Mike Testro

Log in or join to reply