Show/calculate elapsed days between two tasks.

A. E.Member for 6 years 6 months
Created
1
5
0

Is it possible for ASTA to count the total number of days between two tasks? IE, I have an 'implement detour' and a 'remove detour' task at the beginning and end of my project respectiely, with tasks in between, and I need to know how many days the detour will be in place for. Can ASTA tell me this, or do I just have to count it myself? Thanks!

1 reply

Oldest first
  1. 0
    Paul Harris ·

    You may use a Buffer Task and

    You may use a Buffer Task and the calander that it is assigned to will be used to calculate the value of the gap.

    Regards

    Paul E Harris

    Director Eastwood Harris

    Publishers on Oracle Primavera, Microsoft project and Elecosoft (Asta)Powerproject books, videos and training material.

    www.eh.com.au