Has anyone managed to successfully, fully integrated, a BIM 4D model program to Program Schedule with resource to cost.

Allot of examples demonstrate a 3D model interface with a program using the WBS and Activity codes, hit start and follow a

predetermined time line, following no real construction methodology.

The Model answer Im looking for, will demostrate retrospectively, or prospectively if either the schedule or model has any changes made refelcts a new status, balancing the two.

 

Kind Regards

Stephen

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi StephenI have moved your

    Hi Stephen

    I have moved your thread to the new BIM topic.

    Hope you get your answers.

    Best regards

    Mike Testro

  2. 0
    Ben Taunt ·

    Hi Stephen,Is this the sort

    Hi Stephen,

    Is this the sort of thing you mean?:

    http://www.astadev.com/wp-content/uploads/2013/07/Buro-Four-Case-Study.pdf

    Ben @ Asta