using weight

Jafar ZareiMember for 23 years 3 months
Created
1
1
0
Hi Planners,

I want to give weight to all tasks in MS PROJECT that effects on progresses(%complete)
It means I want to have the progress according to the weight not duration.
Please help how?
Thank you



1 reply

Oldest first
  1. 0
    Mk Tse ·
    Use a custom field to store the value of weighting. Copy the required columns from Project to X-L, calculate the progress according to the weighting factor. Copy and paste the progress back to Project.

    (btw, if formula is allowed in Project, no X-L required)

Log in or join to reply