Excel
JS
John SmittMember for 21 years 8 months
- Created
- 12
- 1
0
12 replies
Oldest first- 0JSJohn Smitt ·I’m no expert with excel or planning, infact I’m new to the game, can’t you tell with all the questions. I thought it was a good idea for people to post back when someone asks a question on how to present data. I could have done with this last week doing macros and pivot tables.
- 0AWAlex Wong ·Dear PP
Excel - Interesting Topic
I went to a conference here in Australia, Primavera biggest competitor - guess who - MS Excel
I see engineer try to put together a project report in a excel chart, with activity bars, drawing ...
the first report look great, they try to replicate it for 40 projects, still look very good and management love it.
However, the down turn came when management want to group the projects together, try to find out the critical resource, need to update their progress, then the engineer found out that they are screw up badly. It will take them 3 months to produce such report.
The point I try to make in here is, Excel is good for begineers, when you only have 10 activity you can manage, because it is only a presentation tools that why management love it. When you increase the complexity just a little bit, Excel will fail, fail as a scheduling tool, may be still good as a presentation tool.
Excel skill is needed for presentation of data, scheduling power is require to back up the "Pretty" looking report
In term of having a area to discuss EXCEL for REPORT PRESENTATION I agree, for PLANNING, I totally disagree.
Cheers
Alex - 0PJPhilip Jonker ·Hi Bill/Alex,
If you guys are interested, I could e-mail you an excel spreadsheet, that will blow your minds, and could have been done so simplistically but we have to have the experts.
The point is KISS (Keep it simple stupid) It takes a whole day to update this file, and more, and it robs me of time to walk around and sort out problems. The point is do not develope reporting systems that hook you up to your computor permanently, and if you want these systems, rather employ a data capturer, as it is more than likely you are not looking after the project.
Excel is a tool as is P3, however, P3 or whatever programme you are using is supposed to give the answers. So how can a survey tell us what we need to use. Polls are for politicians, not for engineers. - 0KHKatalin Hovanyi ·Hi,
The Excel is good to do "global changes" outside the Primavera and load back to the Primavera database. A lot of tedious work can be eliminated this way. In this forum we can share little tricks about this database management not about the Excel as a planning tool.
Best Regards
Katalin - 0COCharleston-Joseph Orbe ·Hello,
Excel for planning. Waste of time.
There is a danger in presenting excel as planning tool, generally colorful graphs and bars that come in with excel drawing tools. The problem will start the moment the client or PMT will like the colorful presentation of excel and feel that the project is doing fine because the colors look pleasing to look at.
Believe me guys, in this environment, you will end up doing both excel planning and primavera planning. In addition you will reconcile the figures generated by the two software. As the project moves on, you will look at the contract to ascertain which planning software to use. If the contract require to use P3, then, you will ask "why are we doing excel planning?". At this period, it is too late to back out and use only P3 because you establish a precedent (P3 planning and excel planning).
I do believe excel got a place in planning, as a worksheet to do preliminary planning computation, export import, etc.
Only an idea. IMHO.
Cheers,
Charlie