This website is useless unless your recomendations join

Steve KirkMember for 18 years 4 months
Created
46
5
0
Don’t you think that it would be a god idea for all members to get full access to all of the rates straight away. All the people that i know are already members so that leaves me unable to get to all the rates that i require. Please help me out and take this resistriction of the website

46 replies

Oldest first
  1. 0
    Ife Olyke ·
    Steve,

    ... I am not a PP administrator, but I couldn’t help but respond to your post... I guess you’re refering to Prod-Rates right?... I agree, I think it will be a good idea if all members get full access; but PP requires successful recommendation of at least 2 members before you can access more than 10 results, which I also don’t think is a bad idea... I have recommended a couple of my friends, but only one joined, so I still cannot view more than 10 results per page... And, it’s depressing!!!
  2. 0
    Forum Guest ·
    Hello Planners,

    We have massaged the code for over 1,000 planners who have asked us to bypass this restriction. We have done this for anyone who has asked. If anyone wants full access, simply send us a mail and we will get one of the team to sort it for you.

    To solve this problem and with respect to rates, we are changing the whole system such that we (I am a planner too) can all view and manage the rates data on the site. If anyone wishes to help with this initiative we would love to hear from you.

    Regards....PP Team (volunteer planners)
  3. 0
    Ife Olyke ·
    Hello PP Admin,

    As per you post, kindly bypass the restriction that limits my access to production rates. I’d like to have full access.

    Thanks.
    IO
  4. 0
    Dave Morrow ·
    Hi PP Admin
    Also as per your post, please bypass the restriction so that I can access the production rates. I too would like full access.

    Thanz
    Dabhaid
  5. 0
    Cherie S Blare ·
    Me too.
  6. 0
    Gavin Morris ·
    Agreed. And also the comic sans font isn’t easy to read or very businesslike.
  7. 0
    Forum Guest ·
    Hi All,

    The guys have tweeked the system and you now should have the access you need / have asked for.

    With respect to the font and site layout etc. Big changes are on the way....

    Regards.... PP Team
  8. 0
    Gavin Morris ·
    Thanks, that’s great!
  9. 0
    Dave Morrow ·
    Ta very much PP
    Dave
  10. 0
    Kieran Thomson ·
    Hi guys

    Very much appreciate the effort put in to running this website. I would like to offer my services to assist in the running of the website as a volunteer. Look forward to hearing from you.

    Cheers

    Kieran Thomson (Planner - nobody listens to me, I get the blame when things go wrong, I’m standing at point when the big lumps of brown stuff start hitting the great huge swirly thing, but after all this... I like to turn round at the end of a project and say ’Should have listened to the planner’).
  11. 0
    James Shimmon ·
    PP Admin
    Could you please bypass the restrictions so I can access all Production Rates
    Cheers

    Shimmo
  12. 0
    Colin Blair ·
    me 2
  13. 0
    Mimoune Djouallah ·
    me too please
  14. 0
    Paul Smart ·
    Hi’

    I too would like to by-pass the the restrictions - as all the planners I’ve ever known are already signed up!!

    thank you

    Paul Smart - ID28393
  15. 0
    Chris G. ·
    Hello guys, it seems im one of the lucky guy who have full access with the rates :-) BUT i just wanna know if this rates are based from 1:1 (1-skilled & 1 Helper)?

    Chris
  16. 0
    Gary Whitehead ·
    Hello PP Admin,

    Please could you also bypass the restrictions and give me full access to the production rates. -I’m having the same problem with contacts joining but not being able to ’name-check’ me when doing so.
    Much obliged,

    Gary
  17. 0
    R. Catalan ·
    Hello PP Admin,

    Could you also please bypass the restrictions and give me full access to the production rates?

    Thanks a lot.

    R. Catalan
  18. 0
    Tom Howard ·
    I agree, it’s a daft system. What if you don’t know anyone else in the planning industry ?

    Create some random hotmail addresses and "join" yourself.
  19. 0
    Paul Smart ·
    I have not had my restrictions lifted yet, I’m still waiting for the administrators to sort out this issue.

    paul
  20. 0
    Christian Adrian De Vera ·
    PP Admin

    Another issue to consider is the private message sending. Everytime I try to use it I would end up with.. ’Members Private Message System temporarily turned off while we send some people to see the idiots who want to miss-use the system. We will be back on soon. Sorry! is there anyway we could use is again?

    Appreciate you help...

    Thanks..
  21. 0
    John West ·
    Hello PP Admin,

    With reference to post no.3, please bypass the restriction that limits my access to production rates; I would like to have full access.

    Thank you in anticipation.

    BR,
    John
  22. 0
    Oliver Melling ·
    Hello PP Admin,

    With reference to post no.3, please bypass the restriction that limits my access to production rates; I would also like to have full access.

    Thank you
  23. 0
    Forum Guest ·
    Hi there,

    The Private Message System is now back on. You can read about it on our News Page (link at top of screen).

    We will do our best at the weekend to open up the production rates to the people below who have asked for it.

    In exchange is anyone able to volunteer some time to help us move the rates from the old system into the PP Knowledge Wiki would they contact us via the Private Message System :)

    Thanks.

    In fact, if anyone wishes to volunteer any amount of time (big or small) we would love to hear from them. As we are planners too and are struggling to keep up...
  24. 0
    Oliver Melling ·
    I have some spare capacity to moderate, as i am awaiting to hear about bid success before any major works kick off here.
  25. 0
    John West ·
    I may have lots of spare time in the near future! project near completion and seeking the next contract... :¬)
  26. 0
    Forum Guest ·
    Hello All,

    If anyone has not yet got access per this thread please drop us an email at PPAdmin@planningplanet.com and we will make sure it gets done.

    Thanks.....
  27. 0
    Paul Smart ·
    Thanks for your efforts but...

    I’m still restricted to only 10 items in the production rates

    Paul
  28. 0
    Gary Whitehead ·
    Paul,

    If you email PP Admin at the below address (and include your PP ID number), they’ll sort you out.

    Cheers,

    G
  29. 0
    John West ·
    That’s a big THANK YOU from him; now reviewing the production rates with those for Bulgaria, now there’s a challenge...
  30. 0
    Mike Testro ·
    Hi John

    What are you going on about.

    If you are going off piste then at least keep a relavent thread.

    Best regards

    Mike Testro
  31. 0
    Santhosh kumar Narayanan ·
    I would like to have full access to production rate.

    I am a full time planner since 10 years
  32. 0
    Santhosh kumar Narayanan ·
    Why no action form PP Admin! please let me have full access to production rates!!!!!!!!!!!!
  33. 0
    Gary Whitehead ·
    Santhosh,

    PP Admin are all unpaid volunteers. They don’t get a chance to check the forums every day.

    Be patient. You’ll get access eventually.

    Regards,

    Gary
  34. 0
    Andrew Trainor ·
    Hello PP Admin,

    Could you also please bypass the restrictions and give me full access to the production rates?

    Thanks a lot

    Andy
  35. 0
    Muhammad Anwar ·
    Anyone know how this website is funded and how they generate their revenue??
  36. 0
    Joel Gilbert ·
    Who cares how it is funded, obviously by companies adverts etc.
    One of the main functions of PP in a few years ago was to get the planners jobs, all I see lately is work for the UK and GCC. Other webs are busy taking over in that respect, what is happening ? and don’t hide behind the recession that’s stale news.
  37. 0
    Mike Testro ·
    Hi Guys

    As far as I know the website is run by amateurs who do not take any payment for their time and expertise.

    I do not know if the agencies pay anything for the job listings - probably not.

    If you would prefer this website to be run on a commercial basis how much are you willing to pay for a year’s subscription?

    $100? $200?

    Please let us know so that the admin can put a realistic value on the thing before it is sold to google and they retire to the Bahamas.

    Best regards

    Mike Testro

  38. 0
    Nicolas Igersheim ·
    Hi all and especially moderators,

    I would also like to be bypassed concerning the rates access
    and especially because for the second time,
    my message to
    ’helpdesk@planningplanet.com’ bounced back at me.


    I have never been able to use the recommend page
    as a matter of fact I use PP only in order to solve some
    issues (and help newbies where I can)

    I add said message hereby,


    8<<==================================================

    Bonjour,
    I have been trying now several times over the last few months
    To recommend PP to a few of my friends and colleagues,
    But to no avail.
    In particular, Oxxxxxx.bxxxxxx@eu.rhodia.com
    Never received the message I tried to send him
    Yesterday (three times, with I Explorer and with Chrome)
    Over the dedicated PP feature.
    All I get is this error message, in the best of cases:
    8<=============================================
    Microsoft OLE DB Provider for ODBC Drivers error ’80040e14’
    [MySQL][ODBC 3.51 Driver][mysqld-5.0.18-nt]You have an error in your SQL syntax; check the manual that corresponds to your MySQL server version for the right syntax to use near ’en profiter cette fois’, ’20371’)’ at line 1
    /members/member_recommend.asp, line 42

    =================================================>8

    Are you aware of similar problems and do you have a cure?
    Thanks in advance and
    Best regards
    Nicolas Igersheim

    =======================================================>>88
  39. 0
    Lo Gary ·
    Dear,

    Please allow me access to all the rates as well.



    Thank!


    Gary

  40. 0
    Mike Testro ·
    Hi Lo or Gary (which should I use please)

    You should nevr put any trust in output rates that other planners use.

    Best regards

    Mike Testro
  41. 0
    Abed Prnd ·
    Hi!
    I really wonder
    How to give recommender’s Planning Planet ID No as reference?

    while registering, when being asked to introduce refrences?

    Regards
  42. 0
    Abed Prnd ·
    please kindly describe (with details, In which page?,which link? which field?,..) how my recomendations can join and declare my ID as their refrence?

    Thank you in advance

    Regards,
    Abed
  43. 0
    Abed Prnd ·
    Could you also please bypass the restrictions and give me full access to the production rates?
    My ID:28653

    Thanks a lot
  44. 0
    Dan Mårtensson ·
    Hello Admin,

    Could you please bypass the restrictions and give me full access to the production rates?

    ID:32751

    Best regards

    Dan M
  45. 0
    Nicolas Igersheim ·
    Hello Admin,

    Could you please bypass the restrictions and give me full access to the production rates?

    ID: 20 371

    Best regards

    Nicolas I.
  46. 0
    Rashid Iqbal ·
    Every project has it’s own estimate and the production rates can be taken from there...

    Else for general purpose use MEAN’s Manual..Thanks.

    Regards
    R