Importing MSP into Primavera
Bob FodenMember for 19 years
- Created
- 2
- 1
0
Dear Fellow Planners,
I have to import a number of MSP’s into Primavera 6. I have a unique ID in column "Text1" in MSP I want to be reflected in the Primavera "Activity ID" column but do not know how to change the rule in the import box. As you run through the import criteria it reaches a screen called "Import Confirmation" that then has a section "ACTIVITY" that states "Import Microsoft Project’s Task ID field into :Activity ID". This is where I would like to change it to "Import Microsoft Project’s Text1 field into :Activity ID".
Any ideas ?
Thanks
Bob
I have to import a number of MSP’s into Primavera 6. I have a unique ID in column "Text1" in MSP I want to be reflected in the Primavera "Activity ID" column but do not know how to change the rule in the import box. As you run through the import criteria it reaches a screen called "Import Confirmation" that then has a section "ACTIVITY" that states "Import Microsoft Project’s Task ID field into :Activity ID". This is where I would like to change it to "Import Microsoft Project’s Text1 field into :Activity ID".
Any ideas ?
Thanks
Bob
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?