Claim

Balachandran KandasamyMember for 17 years 9 months
Created
2
1
0
1)Tender Submited 16th January2008,2)Notic of Provisional Intent in 07th May 2008,Agreement on 08th May2008,commencement of the work 05th October 2008

While project stating time matrial prices all gon up.asphalt and concrete prices all gonup.

Inthis condition contractor can ask from ministry loss and expenses.

2 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Bal,

    It depends on the Contract Conditions. If it is a FIDIC contract, then the latest Date of Commencement is 42 days after the signing of the agreement.

    You should have submitted a Program of Works within 28 days from that date (June 18) showing the scope of works and date of completion.

    Then you do a delay analysis by showing the results of the following:

    Agreement: May 8, 2008
    +42 days
    Commencement Date: June 18, 2008
    Actual start of work at site: October 05, 2008
    Critical Activity path delayed by: 109 days

    You have to check your contract and the compensation claused for actions that you can take.

    Good luck,

    Samer
  2. 0
    A D ·
    Check ur tender validity dates

    This is a general scenario in govt. sector in this part of the world and as client, they do ask to increase the validity of the tender submitted from time to time through official letters.

    Check the validity of the tender rates and as sameer suggested u can put ur claim

Log in or join to reply