Sample plans

Martyn CoatesMember for 19 years 2 months
Created
2
1
0
Why dont we have a section of schedules so that if someone is looking for a part of a schedule to aid them in building a full project schedule we have a resource.

I recently swapped industries and would have found it handy to get a past schedule to look at for an idea of how to start out coding a new project and the activities involved.

i find going into see engineers with something that can be looked at is a lot better than starting out with nothing.

2 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Martyn

    Your organisation must have a file of previous projects for you to look in.

    If not map out your own sequence rather than try to crib samples that will not match your current project.

    Best regards

    Mike Testro
  2. 0
    Dieter Wambach ·
    Martyn

    Plans are property of the company for which it was produced. So never they should be published without permission.
    In addition as Mike wrote samples in general won’t match your needs.

    Regards
    Dieter