Calendars in Microssoft Project

Lo GaryMember for 16 years 8 months
Created
1
6
0

Dear,

I used to set in the file/ options / schedule : default start time, default end time , hours per day, hours per week , days per month at the very beginning . Then I set up different calendars for different tasks. However, some calendars may have different start time, end time hours per week with previous file/ option setting. This would come out with duration in decimal places. Please advise.


Regards,


Gary Lo

1 reply

Oldest first
  1. 0
    Jerome Odeh ·

    Durations have decimals

    Durations have decimals because the definition of how many hours make a day, a week or a month is set in the File > Options > Schedule.

    E.g. if you've defined Hours per day as 8, and you've a 12-hour task, the duration of that task in days is 1.5 days irrespective of calendar Start & Finish times.

    You are better off keeping all durations in hours or keeping all calendars with same Start & Finish times.

    ===
    jerome
    PlannersPlace.com