Creting a baseline in MS Project

Fernando TubiaoMember for 17 years
Created
1
3
0
How do you create a baseline in MS Project (2003 & 2007)?

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Fernando,
    Tools, Tracking, Save baseline (Set Baseline in MSP2k7)
    then display the baseline bars in the Tracking Gantt
    Alexandre