Date

Raz SawarMember for 24 years 8 months
Created
3
2
0
I have this curious problem with the date sequence in project 2000. I set a task to start on say Feb. 2001 and finish on Feb. 2002. The gantt chart view shows the task to be over the above stated but when i assign a resource to it the resource usage and graph view show the task to be over a period of feb 2001 - march 2001 and from january 2002 to december 2002. Could this have something to do with the fiscal year settings? Thanks in advance for your help.

3 replies

Oldest first
  1. 0
    Colin Cropley ·
    The default MS Project setup to for resources to be driving. In Tools/Options/Schedule, uncheck the box "New tasks are effort driven" & Default Task Type "Fixed Duration" (both these will stop this problem from happening with new tasks. For existing tasks, In the Task Form for the activity, ensure the Task Type is "Fixed Duration" and the "Effort Driven" box is unchecked. Check the Calendar for the resource assigned to your activity to see if you have any non-work periods defined for the the period of the activity. Hopefully this will solve your problem.
  2. 0
    Se de Leon ·
    Reading your query won't be enough to answer you question. Please email me your file, then after evaluating it, I'll send you my findings. Best regards, Se
  3. 0
    Forum Guest ·
    You have to "check" the calendar for the resource assigned to your activity to see if you have any non-work periods specified for the the period of the activity.

    Am I too late in replying to this one!!

    Jason

Log in or join to reply