Is there anyone who has taken the effort to describe te correct way to transfer a project from MSP2K to P3?
We have already managed to transfer from the microsoft 2000 mpp extension to mpx and into P3 through the conversion tool supplied by Primavera.
The resulting file in P3 then has numerous wrong codes/dates and durations and needs to be reviewed. It is these steps we are looking for.