MS project for managing resources
In the Open Standard
Forum GuestMember for 17 years 8 months
- Created
- 6
- 7
0
Hello,
Have a need to manage multiple resources to multiple projects.
The projects are of different resource usage pattern:
1. Resources are from say common pool
2. There is fixed resources say 3 out of 10 to project1 permanently.
3. Other resources are shared and used across say three projects.
4. One of the project uses resources in both day shift and night shift.
5. Now managing the work load of the resources is key in this case.
Now this is an example of real life situation in managing resoiurces across projects. The resources need to be ordered normally one week ahead from the resource pool. However for emergency services, the resources are allocated based on a duty rouster.
With the above situation , like to have some help / clarifications how we are able to manage the resources.
Please recommend software we could use.
Do you have some tool to share ?
Suggest / provide documents and solution for this if possible.
Thanks
Have a need to manage multiple resources to multiple projects.
The projects are of different resource usage pattern:
1. Resources are from say common pool
2. There is fixed resources say 3 out of 10 to project1 permanently.
3. Other resources are shared and used across say three projects.
4. One of the project uses resources in both day shift and night shift.
5. Now managing the work load of the resources is key in this case.
Now this is an example of real life situation in managing resoiurces across projects. The resources need to be ordered normally one week ahead from the resource pool. However for emergency services, the resources are allocated based on a duty rouster.
With the above situation , like to have some help / clarifications how we are able to manage the resources.
Please recommend software we could use.
Do you have some tool to share ?
Suggest / provide documents and solution for this if possible.
Thanks
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?