Costing: Ms project 2000 sr-1

Mike ElsbreeMember for 22 years 10 months
Created
5
3
0
I want to be able to have a budgeted cost, an actual cost, and the variance. I have been able to do this using baseline, total cost, and variance, but I need to be able to have this data on a task usage graph, that will spread the three across a timescale chart (by week). I would prefer not to have to deal with percentage complete.

I have removed the “actual costs are always figured by ms project” function, but I think that the problem is that I am possibly using the wrong fields for the information.

Any insight that you can offer would be greatly appreciated.

5 replies

Oldest first
  1. 0
    Mohammed Muneeruddin ·
    HI MIKE,

    Are you interested to solve your problem by using another software. I am working as a Planning and cost control Engineer and i have switched over from P3 to CCS (construction computer software ) which i felt ideal for cost control purpose. If so do not hesitate to ask me.

    Regards,

    Muneer
  2. 0
    Mk Tse ·
    Mr. Mohammed Muneeruddin
    The forum is a platform for sharing, if something raise a question or topic for discussion in this forum, we should encourage all to share their suggestions or points of view.

    I, personnal, not support your recommendation "contact youself only". Hope your know how share with us. Thanks.
  3. 0
    Mohammed Muneeruddin ·
    HI FRIEND(S),

    YOU ARE RIGHT, THE WORD I USED MAKE YOU MISUNDERSTAND, WHAT I MEANT IS TO REPLY IN THIS FORUM.

    THANKS

    MUNEER
  4. 0
    Se de Leon ·
    Mike,

    I’m not really sure about your question but my answer is this.

    Pull down view, then select task usage view. Then select the fields you want to see. You can change the timescale to weekly, monthly etc. Please note, you need to have assigned resources to task with unit rates in order for you to see the results.

    Hope this would help.

  5. 0
    Mike Elsbree ·
    Thanks,

    I got what I was looking for by using “cost 1, 2, 3…” fields, and inputting excel type formulas for the data that I needed to acquire. This way, I did not need to input any resources or percentage complete.

    Lastly, I need to change the list of available fields for the timescale aspect of the “task usage” view. Like I said I was able to get the information that I needed using “cost1, 2, 3 …” fields, but they are not available in the timescale chart.

    Mike

Log in or join to reply