I am interested to hear about the experiences of anyone who has used MS Project for Extension of Time submissions or Delay Analysis.

In particular, if the submissions & analysis used ’Time Impact Analysis’ mthodology or other methodologies, such as ’As Planned Impacted’ & ’Collapsed As-Built’.

My experience of using MSProject for EOT/Delay Analysis work has been not very good and I would normally transfer the project data and logic into other database-driven software packages such as P3 or Artemis before using any of the above Delay Analysis techniques.

Have I missed some of the values of MSProject in that it can be used for EOT/Delay analysis work?

2 replies

Oldest first
  1. 0
    Tom Hadley ·
    see my thread re primavera. My recommendation after 20 years of using MS porject is dont use it for EOT, very very risky !
  2. 0
    Roger Gibson ·
    Tom,

    I agree entirely, and I’ve only had 15 years of forensic analysis experience with EOT’s/delays. What is your preferred software?