Gantt Chart doesn’t spread out in Project 200
In the Open Standard
Patrick LiuMember for 22 years 7 months
- Created
- 8
- 5
0
Hi. I have MS Project 2000, and I have inserted the durations of all of my tasks, but once I link all of the tasks (Finish-to-Start), Project doesn’t move the tasks one after another. Instead, all of the links remain in the same position (even though I see the arrows linking each one of them). However, when I bring my file to MS Project 2002 ON ANOTHER COMPUTER (without linking the tasks yet) and link them with the same method, everything works fine (I can see the extension in the Gantt Chart). I tried un-installing the Project 2000 on my computer and installed it again, but it still didn’t work. Does anyone have any idea what’s causing my problem? Thanks in advance.