Gents,

For those who read this forum regular i’m sure you’ve heard this question before.

I have a project 2002 file which I want to convert / import into P3. In previous editions of Ms Project I would have saved it as an MPX and used the MPX converter tool within P3.

Without having to buy a new peice of software such as ’Bluewater’ I think does anyone have any ideas as to convert these files.

Regards
Chris Murray

10 replies

Oldest first
  1. 0
    Paul Smith ·
    You can download the mpp to mpx converter from the Primavera online support site.
  2. 0
    Paul Harris ·
    There is a paper on my website which explains the various methods.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Book Publishers, Training & Consulting
    www.eh.com.au
  3. 0
    Luca Basile ·
    If U send me Your email I will forward U a file I just received to make the conversion.
  4. 0
    Roger Gibson ·
    Luca,

    Could I have a copy of your file conversion please. My email is rogerwgibson2003@yahoo.co.uk

    Many thanks

    Roger
  5. 0
    Sanjeet Teri ·
    I also need the utility to convert .mpp files to P3e/c 4.1
    Kindly forward the same to my email id sanjuteri@yahoo.com

    thanks

    sanjeet
  6. 0
    Sukumaran Subaramaniyan ·
    Hi Luca,

    Could you please forward the converter file to me. My email address is sukumaransubaramaniyan@yahoo.co.uk

    Thanking you in advance.

    Regards.
  7. 0
    Paul Harris ·
    You may use file import to import a *.mpp file into Primavera Version 4.1.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Book Publishers, Training & Consulting
    www.eh.com.au
  8. 0
    Ry All ·
    can u send me a copy aswell please my email addi is analangel@hotmail.co.uk
  9. 0
    Raja Izat Raja Ibrahim ·
    Hi Luca,
    Any extra conveter? Its free isnt it...
    could U send me at this address rizat200@hotmail.com
    Thanks in advance