MS Project Calendar Mods
In the Open Standard
Forum GuestMember for 17 years 8 months
- Created
- 9
- 4
0
Just wondering if there is any way to label specific days on a MSP calendar. We need to blank out several days for things like ’No Power on Site’ so that our contractor knows when to pull his staff back. It would be nice to have a labelled band running vertically down the gant chart with this detail in it - so far I cannot see how this can be done..
9 replies