Skip to content

Maintenence schedule

Gerry MorganMember for 21 years 10 months
Created
2
2
0
Can anyone tell me how to set up a Maintenence schedule in MSP 2003.
I would like to set up a schedule with tasks that last for a year, then have team members log time against the various tasks, but keep the end date from moving out all the time.
basically I just want to keep track of their time worked on any task they may be working on, without showing them over allocated all the time, they could be assiged to many tasks within the same project.
A team member may work on a task one day and then not return to that task for say a couple of days, when this happens it is moving my end date of the schedule.
Thanks.

2 replies

Oldest first
  1. 0
    Raj Maurya ·
    There is one way is that update the activities but don’t reschedule the balance work. Other way is define activity as fixed duration and put end date contraint and define the expected work(in hour or so) to be done during the whole period of work. So when ever you will update resource unit will fluctuate but duration will remain constant. Try this, hopefully it will work.
  2. 0
    Gerry Morgan ·
    Hi Raj

    Thanks. I’ll give it a try.

    Regards, Gerry

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?