Finish Dates different in Project 2003 than Projec
In the Open Standard
Jay McLeodMember for 21 years 8 months
- Created
- 1
- 3
0
As the title states, I have a project, apporx 2000 tasks, that seems fine in project 2000 but when I open it in 2003 it appears to be about 2 months later. I have recopied over the calender from the organizers, tried everything but it still seems to be two months out. The file was sent over to the a local printer and when we got the printout back, it was about two months out as well. Does anyone have any ideas would could be causing this. My new goal is to get it upto Project 2003 since the consulting engineer and printer both have 2003, I can’t have different dates in the project.
Another little weird quirk. I save the file in 2003 as a 2003 version, and open it back it in 2000 and now that project is out by the two months or so.
Has anyone else experienced this and please don’t tell me just to switch to P3 or Suretrack or something, it’s a little late for that and I have to work with what I have.
Another little weird quirk. I save the file in 2003 as a 2003 version, and open it back it in 2000 and now that project is out by the two months or so.
Has anyone else experienced this and please don’t tell me just to switch to P3 or Suretrack or something, it’s a little late for that and I have to work with what I have.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?