"SS+Lag" or "FF"

Nozar NaghaniMember for 22 years 3 months
Created
3
2
0
Hello
Each project manager prefers to see parallel tasks instead of long chains of FS linked tasks.
Especially when tasks are not very small deliverables, there is always the choice to choose SS+Lag or FF instead of FS relationship.
Example: Instead of waiting for AFC foundation drawing, Structural design can start almost a week after start of foundation design (when calculations are available).
I always wonder which link is the best for this purpose (SS+Lag or FF).

What is your experience?


Have fun

Nozar

3 replies

Oldest first
  1. 0
    Bernard Ertl ·
    You may want to do some testing with lags and MS Project if you are using multiple calendars. You may get unexpected results. It appears to use the default project calendar for lags irrespective of the calendars for the tasks being connected by the relationship.

    Bernard Ertl
    eTaskMaker Project Planning Software
  2. 0
    Andrew Pearce ·
    Unless you are using MS Project you should use both!
  3. 0
    Raj Maurya ·
    Activity finish is more important to deliver the project in time so better to use FF and take care of lag (counting as per default caleneder as Bernard said). But there is no harm to use SS with lag to keep Project Managers happy.