Importing MPX from Primavera planner 3.1

Jose FradeMember for 21 years 4 months
Created
5
5
0
In a project that I have now, the client wants to use MS Project. I have done the complete time schedule in Primavera planner 3.1 and used the MPX conversion.

When trying toopen in MSProject I got the message
"An unexpected error ocurred during command execution ....." which is not very clarifying.

Does any one have a hint about this problem ??

Thank’s
JMFrade

5 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Hello,
    What version of MSP are you using?
    Is it in the same language as P3?
    How long is your P3 project, how many tasks? Did you export the time and hour for the date fields?
    MS Project is not smart in using MPX files, and do not understand everything P3 or any other planning software which is able to export to MPX files.
    All the best
    Alexandre Faulx-Briole
  2. 0
    Jose Frade ·
    Thanks Alexandre

    The export facility to MPX is the one built inside the P3 it self. I have no control on the field that P3 exports.

    THe version of MS Project is 2002, and I tryed to use the standard open file choosing type MPX. Also no control about the way MS project imports.
  3. 0
    Alexandre Faulx-Briole ·
    What happens AFTER the message has displayed?
    Does the process stop or ocntinue with additional error messages?
  4. 0
    Philip Jonker ·
    Hi jose,

    Porco Karelio

    You must remember to save to mpx. A further problem, is that MSP does not have code structures, so you have to go through the excercise of putting in the headings, or indents, or whaever they call it, It is a painful excersize, but at the end of the day if that is what they want, deliver. Give me a shout if you are struggling
  5. 0
    Mk Tse ·
    Jose,
    Consider just exprt the necessery information from P3 into DBF. Then import it into MSP.
    The painful process is activity ID re-numbering, not the others.
    Also consider import that MPX into MSP 95 version and then save it into MPP for MSP2002