Progress line in MSP

Ewald LangezaalMember for 21 years 4 months
Created
8
2
0
Hello there, I have a question about progresslines in MSP If I put a progressline into a MSP planning (Not rescheduled)the progressline only shows delays, the tasks ahead of schedule and not 100% complete are not shown as positive progress in other words the progress line stays on the status date. Does anyone knows how to solve this.

8 replies

Oldest first
  1. 0
    Jaco Stadler ·
    Hi Ewald

    Try

    1) Save a Copy (Always save a Copy)
    2) Tools / Options
    3) Tab Called Calculation
    4) Tick Edit to Total Task % >>>>>>> to Status Date.

    This Should do it


  2. 0
    Ewald Langezaal ·
    Thank you for your reply Jaco.
    I already tried this but it does not work.
  3. 0
    Jaco Stadler ·
    Hi Ewald

    I Assume you are Using Remaining Duration & % Complete.

    If Not Try It. I Have just run a test and it is Working
  4. 0
    Sukumaran Subaramaniyan ·
    Ewald,

    What you need to do is once you tick the command, go back to Gantt Chart/Tracking Gantt and change the percentage to 0%. After that re-type the progress percentage. Now you can see the progress line shows progress ahead of the schedule.

    Actually the command is funtioning. You just need to do some test run.

    Regards.
  5. 0
    Ewald Langezaal ·
    Thanks for your swift reply, it is working now, indeed I forgot to reset the % complete and fill it out again.

    I think MSP is still a Mickey Mouse program
  6. 0
    Frans Lasut ·
    Hi, I’m experienced P3 user but currently using MSP.

    I have a question about progress line.

    I have a task that has not started yet. Its baseline start date (I had already saved the baseline) is June 10th, 2006. After rescheduling (The project status date is June 14th, 2004), its forecast start date becomes June 24th, 2006

    In my opinion (as P3 user), the task is only delayed for 4 days. But, when I displayed the progress line in relation to baseline line, why it told me that the task is delayed for more than 2 months?

    How could this situation occur??

    Please advise
  7. 0
    Zhang Haixiang ·
    check display progress lines in relation to "Bastline plan"
  8. 0
    Frans Lasut ·
    I’d already checked the "Display Progress Line in relation to Baseline Plan" BEFORE i asked the question.

    Please go to the link below to see the print screen image for more explanation.

    http://www.geocities.com/taman_eden_ku/progressline.JPG