fix cost for all project

Ersin NamliMember for 21 years 3 months
Created
1
3
0
Hi, how can i identfy a daily fix cost for whole project in ms project.
can i adjust the max. min. crew size in resource leveling
thanks for your answers

1 reply

Oldest first
  1. 0
    Vladimir Liberzon ·
    Create dummy resource with the project daily rate and assign it to the whole project.
    Max/min resource requirements are not supported by this software.