Project/Resource Query

David BladesMember for 22 years 6 months
Created
1
2
0
Planners - please help

I have been asked to update an already started project plan to detail personnel resources. It has a task heading of ’Company Resources’and then 30 sub tasks each being a task to be done. My problem is that as I move down the list and change start and finish dates for some reason the dates of other tasks are being changed? Can you advise on what the contraint type should be? Non of the tasks are linked? I would be most grateful for any advice.

Dave

1 reply

Oldest first
  1. 0
    Sukumaran Subaramaniyan ·
    Dave,

    ????????

    "Tasks are independent and not linked to each other.
    But when you update the start and finish dates for one task the dates for other tasks change automatically."

    Check your schedule again. Go to Format/Layout and check Links. If you marked the links invisible box, remove it and marked the links visible box.

    Now you are able the see the links. Check what are the predecessor and successor for each task and update it accordingly.

    HTH