How to put more than to contraints on a task in MS proj
In the Open Standard
Manulal InasuMember for 21 years
- Created
- 7
- 3
0
Hi,
I am working in a ship repair project and the plan has got a lot of constraints. Any idea how to put more than two contraints on a task?
to explain my question, suppose i have a task "a" with 4 days duration and I have to put both "start no earlier than" and "finish no later than" constraints on this task.
I dont know whether its possible or not in MS Project. So I have developed a planning program in Excel in which it is possible. But it is too slow as the size is around 120 MB and lot of formulae involved. So i thought its better to find out a easier method in MS Project itself.
Can anybody help me please?
I am working in a ship repair project and the plan has got a lot of constraints. Any idea how to put more than two contraints on a task?
to explain my question, suppose i have a task "a" with 4 days duration and I have to put both "start no earlier than" and "finish no later than" constraints on this task.
I dont know whether its possible or not in MS Project. So I have developed a planning program in Excel in which it is possible. But it is too slow as the size is around 120 MB and lot of formulae involved. So i thought its better to find out a easier method in MS Project itself.
Can anybody help me please?
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?