Linking MS Excel to Project

Chris MurrayMember for 22 years 7 months
Created
7
5
0
All,

I’m not getting the graphical results / presentations I require with MS Project.

So, I’m wanting to link my spreadsheet with MS project so that I can perform graphs and Charts. The view I require to link is the resource usage with Peak Units, how do I get this into Excel.

Help Once again!!

7 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Hi there,
    if your spreadsheet has a large nbr of rows, the best if not the only convenient way is to export to Excel.
    Alexandre
  2. 0
    Hannes de Bruyne ·
    Exporting is neither the best nor the only way . Better use VBA to talk with both programms. Do you want an example ? May be I finaly can make somebody enthusiastic for this method. (also available in P3).

    Hannes
  3. 0
    Chris Murray ·
    Hannes,

    Yes any help would be good help. If you can send anykind of module / instructions to my work e-mail I would be happy, chris.murray@ctcmarine.com

    Regards
  4. 0
    John Garay ·
    Hello Chris,

    If the root problem is getting the charts and reports you need from Microsoft Project, I humbly suggest that you take a look at our software - DecisionCharts for Microsoft Project.

    DecisionCharts now has over 90 bundled charts that provide managers with a live, interactive view into their projects (it even has multi-project capabilities). There’s no need to copy and paste into excel - If we don’t have the exact chart or report you need, we can create it. (We do this all the time for customers).

    Please take a look at our website and contact me directly with any questions - Helping managers get the charts and reports they need from Microsoft Project is we do - I would be happy to help!

    Regards,
    John Garay
    DecisionEdge, Inc.
    jgaray@decisionedge.com
    http://www.decisionedge.com
  5. 0
    Ioannis Leontiou ·
    Yes you can directly analyse time scale data into excel. Just activate the Analysis Toolbar and use the command "Analyze TimeScale Data in Excel" and follow the wizard
  6. 0
    Svein Myklebust ·
    You might want to check out Safran for MSP.
    I hav never used it myself, but are a happy user of Safran Procjet and Safran Planner.

    http://www.safran.no/s4msp.htm

    S

  7. 0
    Robyn Brown ·
    Hi All,

    All the information contained in MS Project can be exported to excel\word. Once the end template has been produced. The raw data can be used to Automate this proces, to produce EVM, WBS Forms, Estimate Request Forms etc..


    Regards