MS Project - Early Dates vs Late Dates

Ian ThomsonMember for 23 years
Created
2
3
0
Good afternoon

I am trying to produce both early- and late date curves in MS Project. Have any of you done this? Thanks in anticipation.

2 replies

Oldest first
  1. 0
    Paul Harris ·
    It is possible to get an S-Curve from MSP but it is not the best presentation. Select the tasks a top window Gantt chart, show the resource Graph on the bottom window, right click & select the Cumulative Work, Select Bar styles… and select line for all and/or selected tasks.

    Most people I know export the data to Excel to create S-curves using one of the export functions. I like the Analyze timescale data in Excel function found on the Analysis toolbar. They produce the S-Curves from Excel.

    To make a late curve I make sure I have a closed network and I usually then make all the activities ASAP to create the Late curve. Hopefully someone has a better method than this but I have not found any other method of producing a late curve.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  2. 0
    Robyn Brown ·
    Hi,

    The early late dates Graph for M/S can be produced from within MS Project then exported automaticccaly to excel to provide the S Curve using VBA code.


    Regards

Log in or join to reply