Equipment in MS Project

Andrew LevittMember for 20 years 6 months
Created
2
2
0
Can I tag a resource as equipment so that it doesn’t contribute to the worker-hour (work) calculation, but still can use load levelling and max units, as per work resources?

2 replies

Oldest first
  1. 0
    Paul Harris ·
    Andrew

    Your options are Work or Material.

    You can tag resources, say with a Group, to isolate if it is equipment or people, this may assist.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  2. 0
    Andrew Levitt ·
    Sounds like no then. It’s not isolation that I’m after, but accurate worker-hour calculation together with load levelling and over-allocation notification. thanks for the reply.

    andrew

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?