Projected End Date of Project in MSP

Jatin MammanMember for 20 years 7 months
Created
7
4
0
Dear Planners,
I have saved my project as Baseline and have started monitoring all the activities.
I have started entering the start dates and end dates also.
The project is 20% completed.

Now can i get the Projected End Date of my Project, based on the Dates which i have already entered?
Can the members of the Forum guide me on this one?

Cheers

Jatin

7 replies

Oldest first
  1. 0
    Masood Ahmed Farooqi ·
    after saving baseline , & progress input , you might have a same end date as of base line or another updated end date depending upon teh followinf

    A- PLAIN SCHEDULING

    1. dependin upon link/relationship
    2. actual progress input faster /slower than baseline
    3. any constraint date



    B - SCHEDULING WITH RESOURCE LOADING

    1. in case of efforts driven tsak , availabblity of res. as per relevent res. calander ( if any )

    2. also depending on link & res. availability , later time of among both

    regds

    M . FAROOQI



  2. 0
    Jatin Mamman ·
    Precisely Sir,
    thats what i am searching for, i.e the Updated End Date of the Project.
    In my case, Some Activities have crossed their Basline End Date, and the Actual End Date is greater than the Baseline End Date.

    So i am interested in knowing, if this has caused any change to the Scheduled End Date of the project.

    Would this be reflected in the Project Information (Statistics) part or would it be reflected some place else?
    Because as of now, nothing is being refleted in Proj Info (Stats) barring the Baseline Dates.

    Awaiting your valuable comments

    Regards

    Jatin


  3. 0
    Zhang Haixiang ·
    you can find this information from menu:

    Project - porject information... - finish date

    or you can show the porject summary bar, it also give you the end date
  4. 0
    James Griffiths ·
    Jatin,

    After inputting progress, always remember to "Reschedule Uncompleted Work". If you do not do this, then the project end-date will not change.

    James.
  5. 0
    Masood Ahmed Farooqi ·
    now proceed as follows

    go to TOOL/TRACKING?UPDATE PROJECT/
    select o RESCHEDULE UNCOMPLETED WORK TO START __*_____

    * date of progress

    finally select O ENTIRE PROJECT

    goodluck

    MASOOD AHMED
  6. 0
    James Griffiths ·
    Thankyou Masood. I was being lazy and hoped that he himself would discover how to do this. It should be in the HELP file.

    James :-)
  7. 0
    Jatin Mamman ·
    thank you sir,

    am finally able to break the Da Vinci Code of my project


    Cheers

    jatin

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?